2025 Sidewalk Program
The contractor is finishing up sidewalk work in Phase 3 and starting work along major roads.
Landscaping work continues in Phase 2 & 3.
Once the regular sidewalk work is complete the contractor will work on their punch list of repairs.
Schedule:
- Phase 1: Working east to west between 13 Mile Road and Normandy Road
- Phase 2: Working west to east between Normandy Road and 14 Mile Road
- Phase 3: Working west to east between 14 Mile and north city limits.
If property owners wish to discuss the proposed sidewalk replacement with the project inspector, please call 248.246.3260 to schedule an appointment.