CAP2410 Water Main Improvements
All water main installation and connections are complete for both streets, only roadwork is remaining.
On Northwood, the contractor is finishing concrete work in various areas along the corridor including sidewalk ramps and curbing,.
On Sycamore, the contractor will be working on the driveway approaches for the north side of the roadway.
The contractor is also finishing some intersection work at Maplewood and at Bonnie View Drive this week.