CAP2306 Rochester Road
The contractor has switched the traffic control to Phase 2 and has started work on the west side of the roadway. The contractor will be removing pavement, curbing, sidewalks and driveways. Large driveways to commercial properties or multi-family properties will be removed in halves to maintain access for residents. The smaller driveways will be filled in with stone once removed to maintain access.
The first layer of asphalt has been placed on the east side of the roadway and one lane is open in each direction for traffic. Use caution when driving as sewer structures will not be flush with the roadway until final paving towards the end of the project.
The landscaping contractor is working on lawn restoration and sprinkler repairs on the east side of the roadway where work is complete.
Turn Restrictions and Closures:
Left turns will not be allowed for northbound and southbound traffic at 12 Mile Road, Girard Avenue and at 13 Mile Road during construction to avoid backups. Northbound Rochester Road will be completely closed between Gardenia Avenue and Dewey Street. Local access to the Oakview Cemetery and Rite Aid will remain open.
More information about the lane conversion can be found at:
www.romi.gov/RochesterRoad