CAP2315 Asphalt Resurfacing
The project streets shown in purple on the project map have been divided into three phases as shown below.
Phase 1
Lawn restoration will continue this week of Phase 1 streets.
On Hawthorn, paving will be rescheduled to be done during the next paving session.
On Forest, storm sewer repairs continue and should finish up this week. Once complete, the contractor will replace the driveway approaches that were out of spec (too steep) for those affected residents, weather permitting.
During the sewer work, Forest will be completely closed from Alexander to house #524/527, and residents within this section will not have access to their driveways.
On N. Wilson, the contractor will continue any remaining lawn restoration work. Final paving will occur next paving session.
Phase 2
On Etowah, the contractor will continue work on the west side of the roadway this week, working north to south.
On Hoffman, the contractor has completed curb replacement work. The roadway will be scheduled for milling once work on Blair progresses.
On S. Blair, concrete work continues this week, on the west side of the roadway.
Phase 3
On Wellesley, curb work may begin later in the week on the east side of the roadway, weather permitting.
Work on S. Edison, S. Wilson, and Tufts will likely begin mid-July as work on other streets progresses.