CAP2315 Asphalt ResurfacingThe project streets shown in purple on the project map have been divided into three phases as shown below. Phase 1Lawn restoration will begin this week of Phase 1 streets. On Hawthorn, paving will be rescheduled to be done during the next paving session. On Forest, storm sewer deficiencies were found and repairs need to be performed. Last week the contractor finished the eastern pipe section. This week they will work on the section east of Oakmont, and the section west of Oakmont will be completed next week. During the sewer work, Forest will be completely closed from Alexander to house #524/527, and residents within this section will not have access to their driveways. On N. Wilson, the contractor will continue lawn restoration work. Final paving will occur next paving session. Phase 2On Etowah, the contractor will begin work on the west side of the roadway after completing work on S. Blair, likely Friday. On Hoffman, the contractor has completed curb replacement work. The roadway will be scheduled for milling once work on Blair progresses. On S. Blair, concrete work continues this week, on the west side of the roadway. Phase 3Construction on these streets is scheduled to begin mid-July. The contractor may begin saw-cutting the concrete in advance.
|