CAP2335 Road Reconstruction
Parkdale (Vermont to N. Wilson)
The roadwork is substantially complete and the contractor will begin working on lawn restoration, and finishing some minor concrete work.
Woodsboro
This week the contractor will be cleaning and prepping to place the new driveway approaches. The roadway has been poured and will be-opened once the concrete has strengthened enough to drive on again. (Paving on Vinsetta at the intersection is scheduled for Thursday.)
E. Hudson
The contractor will be grading and prepping the roadway for the new pavement this week.
Helene
The contractor is starting work on Helene this week. The contractor will begin work on the north half of the block, stopping at Middlesex (so that Middlesex residents still can access their homes during construction. The contractor will be removing pavement, curbing and driveway approaches, starting on the west side of the roadway.