CAP2315 Asphalt Resurfacing
The project streets shown in purple on the project map have been divided into three phases as shown below.
Phase 1
On Hawthorn, the contractor is continuing work, most of the concrete on the south side of the roadway is now complete and the contractor has begun work on the north side of the road. The contractor will be replacing some curbing and driveway approaches.
On Forest, the contractor has completed concrete work on the south side of the roadway. This week, the contractor will be re-locating a fire hydrant and begin curb removals on the north side later in the week.
On N Wilson, the contractor plans to begin work on the east side of the roadway, doing curb and driveway approach removals.
Phase 2 & 3 - Underground Work
The city's underground contractor will begin work on Etowah (Phase 2) and Wellesley (Phase 3) this week to install new storm sewer and catch basins, prior to the road contractor arriving on the blocks.