2023 project map

2023 Construction Project Map available now!

Use the map above to see if a project is affecting your street. The city realizes construction will be an inconvenience and all efforts to expedite the work will be utilized to minimize traffic conflicts and access to various properties abutting the project.

Notices of Construction have been mailed to affected residents and copies are available online here.

CAP2306 Rochester Road

This week the contractor is continuing work removing pavement on the east side of the roadway heading north. Once complete the contractor will begin installing underdrain along the edge of the roadway and will begin construction the east side shoulders in areas where no water main work is planned.

Turn Restrictions and Closures:

Left turns will not be allowed for northbound and southbound traffic at 12 Mile Road, Girard Avenue and at 13 Mile Road during construction to avoid backups. Northbound Rochester Road will be completely closed between Gardenia Avenue and Dewey Street. Local access to the Oakview Cemetery and Rite Aid will remain open.

More information about the lane conversion can be found at: www.romi.gov/RochesterRoad

CAP2308 Major Road Improvements


Vinsetta Boulevard:

This week the contractor will finish up the underground work on drainage structures and begin prep for concrete work, including curbing, gutter, sidewalk ramps and bump outs.

Normandy Road:

The full road closure is tentatively scheduled to begin the week of May 1st, and the contractor will begin underground water main installation between Crooks and Delemere. Intermittent closures may occur this week as the contractor delivers materials and equipment to the site.

Normandy Road will be closed to thru traffic throughout construction. Residents with driveways on Normandy will still be able to enter the construction zone via the side streets to access their property. Businesses should direct their patrons, employees and deliveries to use Coolidge to access Normandy Road to minimize conflicts with construction work.

Lincoln Avenue:

The contractor will continue concrete work this week, replacing the sidewalk ramps. The road is closed to thru traffic, but access to businesses and residences will remain open. The contractor tentatively plans to mill the roadway surface the week of May 8th.

CAP2305 Concrete Repair Program

The contractor is continuing work in the northwest area of the project limits, near Greenfield and 14 Mile.  The contractor is removing sections of pavement working their way south and east and will pour the new pavement later this week.

Work will only be performed on one side of the street at a time, to maintain access for residents throughout construction. Only the worst sections of concrete pavement will be removed and replaced, not the entire roadway. If driveway access will be affected, residents will be notified the day beforehand via doorhanger.

The map below shows the project streets highlighted in BLUE.

CAP2305 map excerpt

CAP2310 Water Main Improvements

 Construction starts this week on Longfellow. The contractor will be saw-cutting and removing pavement in preparation for new water main installation.

CAP2315 Asphalt Resurfacing

The project streets shown in purple on the project map have been divided into three phases as shown below.

Phase 1

The contractor has begun work on Hawthorn, replacing concrete on the south side of the roadway. The contractor also plans to start concrete work on the south side of Forest this week.

If residents will lose driveway access, they will be notified via doorhanger at least 24 hours in advance.

CAP2315 Phasing

CAP2335 Road Reconstruction

On Parkdale (Vermont to N. Wilson) the contractor will be grading and installing the aggregate road base this week.

On Woodsboro, the contractor will be removing pavement and installing new water main between Forestdale and the dead end.

CAP2335 street list

CAP2302 Sidewalk Improvement Program

The sidewalk improvement program is tentatively scheduled to begin in June. Notices of Construction with estimates will be mailed to property owners in April.

If you disagree with the estimate for sidewalk replacement adjacent to your home, you can call the engineering office to schedule an appointment to meet with the inspector for the project and review the sidewalk work.

picture showing target area for 2023

RCOC Greenfield & Normandy Roundabout

The Road Commission for Oakland County (RCOC) will be installing a roundabout at the intersection of Greenfield Road and Normandy Road this summer. The intersection will close when construction begins, the week of June 12th.

View the construction flyer

Please note that construction schedules are tentative, and may change based on weather delays, subcontractors or substantial field modifications. These updates are based on the information currently available.

You can visit www.romi.gov/currentprojects to view the 2023 project map, find copies of mailed construction notices, and read about the city's various construction projects.